www.industryemea.com
11
'19
Written on Modified on
MEDIAWORLD
First Danieli Bell Annealing Furnaces in Russia, for Nlmk
Two-phase project will heat-treat steel wire coils in nitrogen atmosphere.
NLMK Metiz selected Danieli Centro Combustion to supply a new bell annealing furnace installation for the Berezovki facility.This new system will heat-treat (recrystallize) steel wire coils in 100% N2 atmosphere. The charges will be 21-t coils in seven stacks of three coils each.
The project consists of two phases: In Phase 1, DCC will supply two bases, one heating hood, two inner covers, and one cooling hood. Phase 2 will match the first part of the project.
The furnaces will have a direct coupled base fan; special design diffuser and plenum; hydraulic locking system; and silicon-carbide head burners, each one with its own recuperator.
DCC will supply all mechanical, electrical and automation equipment, and provide technical assistance during erection and commissioning.
www.danieli.com