Plazar Manutention furthers the expansion of the Amada plant with a 30-tonne overhead crane
Plazar Manutention, industrial handling specialist and partner of handling equipment manufacturer Verlinde, has designed and commissioned a 30-tonne overhead crane at the machine tool production plant Amada. Setting up an installation for the handling of this type of load, extremely heavy but fragile, requires great expertise and highly dependable handling equipment.

A custom designed and built overhead crane to meet the specifications for the handling of new types of machine tools
It involved installing a new overhead crane with a load capacity of 30 tonnes in an adjacent building where machine tools are stored and loaded on trailers. Amada recently initiated the production of new machine tools with an increase of weight from the former 17 tonnes to 25 tonnes. The storage facility had to be much more spacious above all to accommodate a new overhead crane as load capacity of the existing ones was limited to 20 tonnes. The plant produces some 20 machines monthly.
The selected Verlinde lifting equipment meeting handling requirements is a VT4 hoist in the EUROBLOC range. This range alone, catering for the needs of loads from 800 to 80,000 kg has been awarded 13 patents. This type of hoist is fitted for instance with variable speed travel for more accurate positioning of loads together with short pulley block vertical movement enabling almost TVL. Entirely safe, it is fitted with an e-monitoring system for the recording of types of duty of the hoist (MT2 unit) and 4 fully streamlined travel wheels.
The constraints of the Installation
The constraints were first and foremost structural; as an existing building was involved, the floor had to be sounded to make sure it could support such a load. A 6 m bore hole was ordered by a surveyor with the aim of determining the thickness required for the concrete layer at the base of the overhead crane, along with its steel runway. Terrain stability for this type of application is indeed crucial.
Plazar Manutention custom-designed an overhead crane with a load capacity of 30 tonnes that was delivered on site as partial assemblies. It was assembled in one week. From the boring operation to commissioning in April 2020, the project took just 45 days. Plazar Manutention's responsiveness was much appreciated. Mr. Desveaux concluded: "we had already gained the trust of Amada by our quality of service and our recommendations throughout the ten years of our collaboration. However, this resulted in a boost to their trust!”